Project Phoenix

Details

Client :

Imperium

Main Contractor:

Norwest Holst

Architect:

Douglas and Warner

Engineer:

Richter Associates

Value:

~£15.5m

Duration:

49 weeks

Completed:

2011

Project Phoenix

Groundworks, drainage and construction of a reinforced concrete frame within an existing warehouse without accutane meds shop online https://accutane4acne.com/ accutane for acne the use of tower cranes. Design responsibility to co-ordinate with structural engineer, architect and services engineer to progress and incorporate the design development into the works.