Details | |
---|---|
Client : Imperium | Main Contractor: Norwest Holst |
Architect: Douglas and Warner | Engineer: Richter Associates |
Value: ~£15.5m | Duration: 49 weeks |
Completed: 2011 |

Groundworks, drainage and construction of a reinforced concrete frame within an existing warehouse without Lasix meds shop online lasix online pharmacy the use of tower cranes. Design responsibility to co-ordinate with structural engineer, architect and services engineer to progress and incorporate the design development into the works.